Construction Administration Guide

Commercial Construction Loan Draw Process: Inspection, Lien Waivers & Funding

Commercial construction financing is not disbursed as a lump sum at closing. Instead, construction loan proceeds are held in a lender-controlled facility and disbursed in monthly installments ("draws") as construction milestones are completed. Managing construction draws effectively ensures contractor cash flow while protecting the lender from mechanic’s liens.

Indicative Underwriting Matrix

Standard Billing Forms AIA Document G702 & G703 Application and Certificate for Payment with detailed Schedule of Values
Funding Turnaround Time Typically 10 to 15 Business Days Measured from formal draw submission to wire transfer disbursement
Independent Site Inspection Third-Party Inspecting Architect (TPIA) On-site physical inspection verifying percent of work completed in place
Retainage Holdback Rate Typically 5% – 10% Withheld Withheld from each draw and released upon substantial completion and punch list
Lien Waiver Requirement Conditional & Unconditional Waivers Required from General Contractor and all major subcontractors and material suppliers
Title Update Requirement Title Date-Down Endorsement Title company confirms zero interim mechanic’s liens have been recorded

All construction draw procedures must comply with credit agreement covenants and state mechanic’s lien statutes. BancorpOne provides capital advisory and coordinates construction loan draw workflows for developers nationwide.

The Monthly Commercial Construction Draw Cycle

Commercial construction draw administration operates on a disciplined monthly cycle designed to ensure that the loan remains in balance (remaining undisbursed loan funds equal or exceed remaining construction costs to complete):

  • 1. Contractor Draw Request Submission: The General Contractor (GC) compiles the monthly payment application using standard AIA G702 (Application for Payment) and AIA G703 (Continuation Sheet detailing the itemized Schedule of Values).
  • 2. Lien Waiver Documentation: The GC delivers Conditional Lien Waivers for the current draw amount and Unconditional Lien Waivers for all funds disbursed in the preceding draw, covering all primary trade subcontractors and materials suppliers.
  • 3. Third-Party Inspecting Architect Site Visit: The lender dispatches an independent consulting engineer or inspecting architect to the job site. The inspector verifies that materials are physically installed in place, reviews building code progress, and issues a formal written report approving the draw percentage.
  • 4. Title Date-Down Endorsement: The title insurance company performs an updated title search dating from the last draw, issuing a Title Date-Down Endorsement confirming that no contractor mechanic’s liens have attached to the real estate.
  • 5. Lender Wire Disbursement: Upon internal credit approval of the architect’s report and title endorsement, the lender wires approved draw funds directly to the developer’s construction escrow account or directly to the GC.

Understanding Construction Retainage and Contingency

To ensure contractors complete final finish work, punch lists, and deliver certificates of occupancy, commercial lenders mandate a 5% to 10% "Retainage Holdback" on all hard cost billings.

Retainage is accumulated across every monthly draw and is only released after the project achieves Substantial Completion, receives a permanent Certificate of Occupancy (CO) from the municipality, delivers final unconditional lien releases from all trades, and passes final lender inspection.

Direct Underwriting Intelligence

Frequently Answered Financing Questions

Verified answers to common borrower and broker inquiries regarding loan sizing, guidelines, and execution.

Loan-in-Balance Test

What is an "out-of-balance" construction loan and how is it corrected?

A construction loan is out-of-balance when the remaining undisbursed loan funds are less than the remaining costs required to complete the project due to budget cost overruns.

When this occurs, the lender halts all future draw funding until the developer injects additional cash equity into a dedicated interest escrow to re-balance the loan.

Review Construction Guidelines →
Stored Materials Billing

Can a developer draw construction loan funds for materials stored off-site?

Generally no, unless specifically pre-approved by the lender under strict off-site stored materials covenants, including bonded warehouse storage and specialized casualty insurance.

Lenders mandate that materials must be installed in place or securely stored on the insured construction job site before loan proceeds are released.